[2016-New] 100% New Updated C_PM_71 Practice Tests Questions Lead2pass Helps Pass C_PM_71 Successfully (31-40)

By | July 23, 2016

2016 July SAP Official New Released C_PM_71 Q&As in Lead2pass.com!

100% Free Download! 100% Pass Guaranteed!

There is no need to hassle if you are stuck in the C_PM_71 exam difficulties, Lead2pass will assist you right through C_PM_71 exam with C_PM_71 PDF and VCE dumps. Lead2pass delivers the most comprehensive C_PM_71 exam preparation material, covering each and every aspect of C_PM_71 exam curriculum. We ensure you 100% success in C_PM_71 exam.

Following questions and answers are all new published by SAP Official Exam Center: http://www.lead2pass.com/c-pm-71.html

QUESTION 31
You are in the Project Preparation phase and want to refine the implementation scope. One part of the implementation scope focuses on the business processes affected by the project. Why is it important to define a Business Process Hierarchy? Note: There are 3 correct answers to this question.

A.    It is needed to manage external stakeholder expectations.
B.    It helps you to organize and execute Blueprinting workshops.
C.    It allows you to capture deliverables such as requirements and process flows in a structured way.
D.    It is the binding structure for value delivery.
E.    It helps you to develop a detailed cost management plan.

Answer: BCD

QUESTION 32
The project manager plans the quality assurance for the project and considers using the Project Management Review service as an impartial analysis.
When is the service delivered according to ASAP?

A.    During the Operate phase, once the project is completed
B.    After each project phase, delivered in five steps
C.    In the Final Preparation phase, delivered by the project manager
D.    During the realization phase, after each project quality gate is completed

Answer: B

QUESTION 33
What is the expected outcome of core configuration in the Realization phase?

A.    The baseline of the SAP system is configured and ready for further development of enhancements.
B.    The SAP system is ready for the final configuration cycle testing.
C.    The scenario configuration documentation is 100% completed and ready for sign–off.
D.    Master data test cases are documented and test results are available prior to final data load-

Answer: C

QUESTION 34
Which of the following are characteristics of IT governance in the context of ASAP methodology? Note: There are 3 correct answers to this question.

A.    IT governance is planned, defined, and set up during the implementation project.
B.    IT governance is optimized during the Operate phase.
C.    IT governance is set up right after production cutover in the earl}.r stages of the Operate phase.
D.    IT governance is defined and completer put in place in the Project Preparation phase, as part of the project standards.
E.    IT governance is covered by ASAP methodology.

Answer: ADE

QUESTION 35
What do you call the prioritized delta list that is a result of the Business Blueprint phase in Agile ASAP?

A.    Project change log
B.    Project risk list
C.    Project issue log
D.    Project backlog

Answer: D

QUESTION 36
What is the SAP tool set for the solution demo approach? Note: those 3 are correct

A.    Proof of vision supported through SAP Application visualization by iRise
B.    Proof of concept through prototyping
C.    Predefined SAP Solution (Rapid Deployment Solutions)

Answer: ABC

QUESTION 37
You are a project manager in the Business Blueprint phase of an implementation project. You have been advised byyour project team members that there is an influential stakeholder who is liker to resist the process changes introduced by the project. Which approach, recommended in ASAP, will help you to understand the attitude of this stakeholder and the level of impact this stakeholder has on your project?

A.    Preparation of project standards
B.    Communication planning
C.    Stakeholder analysis

Answer: C

QUESTION 38
Which of the following project and operational standards are defined by the Technical Solution Management work stream during the Project Preparation phase? Note: There are 3 correct answers to this question.

A.    Determine Technical Operations
B.    Determine Business Process Operations
C.    Determine Change Control Management Procedure
D.    Determine Application Incident Management Procedure
E.    Determine Test Management Procedure

Answer: ACD

QUESTION 39
What are the four key lifecycles covered by ASAP?

A.    Project management lifecycle / Solution management lifecycle / Risk management lifecycle / Technical management lifecycle
B.    In Value management lifecycle / In Project management lifecycle / on Knowledge management lifecycle / It Cost management lifecycle
C.    Scope management lifecycle / Project management lifecycle / Quality management lifecycle / Value management lifecycle
D.    Process management lifecycle / Value management lifecycle / Project management lifecycle / Application management lifecycle

Answer: D

QUESTION 40
Which Application Life Cycle Management (ALM) process deals with the storage and collection of detailed information about business processes and system settings?

A.    Business Process Operation
B.    Solution Documentation
C.    Solution Implementation
D.    Test management

Answer: B

We highly recommend our C_PM_71 dumps. Comparing with others’, Lead2pass is the most credible and authentic source of information on C_PM_71 exam and we strive to keep our C_PM_71 dumps up-to-date and reliable on a consistent basis. Our exam preparation material is rich in variety. We offer C_PM_71 PDF format and C_PM_71 practice test with free VCE player. That’s the reason why many candidates choose Lead2pass.

2016 SAP C_PM_71 exam dumps (All 85 Q&As) from Lead2pass:

http://www.lead2pass.com/c-pm-71.html [100% Exam Pass Guaranteed]